Assuming the pipe line is ready meaning free of any unwanted materials or object inside, the cleaning machine can go ahead without the inspection machine to pre-video the pipeline. It can start doing the cleaning process on each girth weld (standard 15 G.W. per string). After Cleaning the whole string and verified that it is set to go for coating application it will move to the next pipe string to start cleaning again.
On this stage the girth weld now is clean and ready for coating. In this process the girth weld will be subject to heating by means of induction heating using induction coils prior to coating application. Post cure heating will be applied after internal coating is done which is also the applied temperature for external coating.
This is the process in which the applied internal coating is subject for holiday test, mils measurement and at the same time checking the physical appearance of the applied coating if there is any presence of bubbles, orange peel or any abnormalities on the surface of the applied coating.
On this stage right after the internal coating process is done and post curing heating (application temperature of external coating also) has been applied for curing the internal coating, the external coating process could begin and start the application of external coating right away.